If flexible budget amount is $27000 and flexible budget variance is $12000, then actual result amount would be
A. $27,000
B. $15,000
C. $39,000
D. $49,000
Answer: Option C
Solution(By Examveda Team)
Actual result = Flexible budget amount + Flexible budget variance= $27000 + $12000 = $39,000