If flexible budget amount is $7500 and sales volume variance is $6500, then static budget amount would be

A. $7,500

B. $6,500

C. $1,000

D. $10,000

Answer: Option C

Solution(By Examveda Team)

Static budget amount = Flexible budget amount - Sales volume variance
= $7500 - $6500 = $1,000.

This Question Belongs to Management >> Management Accounting