If flexible budget amount is $7500 and sales volume variance is $6500, then static budget amount would be
A. $7,500
B. $6,500
C. $1,000
D. $10,000
Answer: Option C
Solution(By Examveda Team)
Static budget amount = Flexible budget amount - Sales volume variance= $7500 - $6500 = $1,000.