If number of units are 3000 and per unit price is $500, then flexible budget variable will be
Answer & Solution
Correct Answer:
Option
A
Flexible budget variable = Number of units × per unit price
= 3000 × $500 = $1,500,000
= 3000 × $500 = $1,500,000