If sales budget variance for operating income is $68000 and static budget amount is $19000, then flexible budget amount will be

A. $47,000

B. $57,000

C. $87,000

D. $97,000

Answer: Option C

Solution(By Examveda Team)

Flexible budget amount = Operating income + static budget
= $68000 + $19000 = $87,000

This Question Belongs to Commerce >> Costing