If the R.L’s of canal bed level and high flood level of drainage are 212.0 m and 210.0 m respectively, then cross drainage work will be

A. aqueduct

B. superpassage

C. syphon

D. syphon aqueduct

Answer: Option A


This Question Belongs to Civil Engineering >> Irrigation Engineering

Join The Discussion

Comments ( 12 )

  1. Hossayn Fedayi
    Hossayn Fedayi :
    9 months ago

    Gyz Option C is Correct..

    Because the R.L is measured on Staff with reference to a benchmark.

    so low reading on staff means high elevation so ultimately 210 HFL of dranige will be higher than 212 of canal bed.

    so Syphon need to be provided

  2. Ayush Meena
    Ayush Meena :
    3 years ago

    Obslutly ans will be aqueduct so correct option should be A

  3. Rohit7 Katte7
    Rohit7 Katte7 :
    3 years ago

    Aqueduct

  4. Mustafa Hussein
    Mustafa Hussein :
    3 years ago

    Its aqueduct

  5. Asad Ullah
    Asad Ullah :
    4 years ago

    it is aqueduct

  6. Abhishek Raj
    Abhishek Raj :
    4 years ago

    Wrong answer
    A is correct

  7. P K
    P K :
    4 years ago

    Mr. Santosh Kr. Garg" Page nos. 486 & 487, Example 14.1....answer is . aqueduct

  8. SOUMITRA MUDI
    SOUMITRA MUDI :
    4 years ago

    Hence, only option (A) Aqueduct will be the most appropriate answer.

  9. SOUMITRA MUDI
    SOUMITRA MUDI :
    4 years ago

    As per "Irrigation and Hydraulic Structures by Mr. Santosh Kr. Garg" Page nos. 736 & 737, Example 14.1, it has been clearly mentioned "Canal Bed Level (RL = 212.0 m) is much higher than the High Flood Level of Natural Drainage (RL = 210.0 m); Hence, Aqueduct should be constructed."

  10. Bhageerathy K
    Bhageerathy K :
    4 years ago

    It is aqueduct

  11. Muhammad Saqib
    Muhammad Saqib :
    4 years ago

    Aqueduct or syphon aqueduct,, right answer

  12. Mangesh Lanjewar
    Mangesh Lanjewar :
    4 years ago

    I think aqueduct is correct answer