If the value of ore is Rs. 600 per tonne, production cost Rs. 400 per tonne, and cost of overburden removal Rs. 50 per m3, the break-even stripping ratio in m3/tonne is

A. 4 : 1

B. 3 : 1

C. 1 : 3

D. 1 : 4

Answer: Option A