In a mine for one shovel six trucks are assigned. The shovel loading time per truck is 5 min, and truck cycle time 20 min. Calculate the match factor.
A. 0.66
B. 1.00
C. 1.20
D. 1.50
Answer: Option D
Related Questions on Introduction to Mining Engineering
A. Normal distribution
B. Skewed distribution
C. Lognormal distribution
D. Poisson distribution
A. 3 level heading district
B. 4 level heading district
C. 5 level heading district
D. 6 level heading district
It is very difficult to control shaley roof if coal is not left with the shale why?
A. It is weak in nature
B. It has weathering effect
C. It has great affinity to absorb moisture and get departed from immediate roof
D. It reacts with coaly surface