In block caving operation the draw points are placed at 20 m centre to centre, with the pillar width 3.5 m as shown in figure below. The muck is assumed to have zero cohesion and 35 friction angle. The height of draw cone (h) in m is
Introduction to Mining Engineering mcq question image

A. 12.5

B. 14.6

C. 15.8

D. 16.5

Answer: Option C