In budget hierarchy, material handling cost is

A. fixed manufacturing cost

B. batch level cost

C. per unit cost

D. factory overall cost

Answer: Option B

Solution(By Examveda Team)

In budget hierarchy, material handling cost is batch level cost. A batch-level cost is a cost related to a group of units, but which is not associated with specific individual units.

This Question Belongs to Management >> Management Accounting