Examveda

In permanent lining, in hard rock the excavation reduced to finished diameter of the shaft and continuous thus for . . . . . . . . below.

A. 1 - 2 m

B. 2 - 3 m

C. 3 - 4 m

D. 4 - 5 m

Answer: Option C


This Question Belongs to Mining Engineering >> Coal Mining