In the Boston Big Dig project, what was the primary method to support deep excavations?

A. Rock bolts

B. Slurry walls

C. Pile rafts

D. Gabion walls

Answer: Option B

Solution (By Examveda Team)

The Boston Big Dig used slurry walls extensively. These are deep trenches filled with bentonite slurry to stabilize soil before pouring reinforced concrete walls in-situ.