In which of the following layouts, the lines need to the balanced
A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer: Option B
A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer: Option B
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion