Match the following
List-I (Techniques of Work Measurement) | List-II (Purpose) |
a. Direct Time Study | 1. Amount of time |
b. Synthesis Method | 2. Time Values |
c. Analytical Estimating | 3. Job |
d. Predetermined Motion Time | 4. Basic time |
A. a-1, b-3, c-2, d-4
B. a-3, b-4, c-1, d-2
C. a-1, b-2, c-3, d-4
D. a-1, b-4, c-3, d-2
Answer: Option C