Match the processes in Group I with the objectives in Group II.
Group I | Group II |
P. Vacuum Arc Degassing (VAD) | 1. Primary iron making |
Q. LD | 2. secondary steel making |
R. COREX | 3. Direct smelting |
S. Blast Furnace | 4. Primary steel making |
A. P-3, Q-4, R-2, S-1
B. P-4, Q-3, R-1, S-2
C. P-3, Q-2, R-1, S-4
D. P-2, Q-4, R-3, S-1
Answer: Option B