21
A dragline is required to remove 3,00,000 m3 of rock per month on the bank volume basis. Consider the following data for the dragline operation.
Effective working hours per month = 450
Bucket fill factor = 0.8
Cycle time = 65 s
Swell factor of the rock = 1.25
The minimum bucket capacity of the dragline in m3 is
Effective working hours per month = 450
Bucket fill factor = 0.8
Cycle time = 65 s
Swell factor of the rock = 1.25
The minimum bucket capacity of the dragline in m3 is
Answer & Solution
Answer: Option
D
No explanation is given for this question. Let's Discuss on Board