51
In the form of a square pyramid blasted material of 7368 m3 by volume is accommodated. The height of the pyramid is 2.4 m. Calculate surface area in m2
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
52
It is the mining method in which masses, panels or blocks of ore are under cut to induce caving, permetting the broken ore to be drawn off below.
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
53
An arrangement that prevents oversized rock to pass.
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
54
The method of stoping selected in strong to weak, fairly steep are with weak host rock.
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
55
The level roadways are dipping at a mild gredient between . . . . . . . .
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
56
Channel sampling also called . . . . . . . .
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
57
In cut and fill stope the main purpose of back filling is to . . . . . . . .
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
58
A small portion of the ore body collected and analysed to estimate the average mineral content of the ore body called . . . . . . . .
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
59
Stoping is always started on each side of . . . . . . . . direction.
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
60
Cut and fill stoping can be done by . . . . . . . .
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board