PERT
A. Provides an approach for keeping planning up-to-date
B. Provides a way for management to require that planning be done on a uniform and logical basis
C. Permits management to foresee quickly the impact of variations from the plan
D. All of the above
Answer: Option D
Solution(By Examveda Team)
PERT- Provides an approach for keeping planning up-to-date
- Provides a way for management to require that planning be done on a uniform and logical basis
- Permits management to foresee quickly the impact of variations from the plan
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion