PERT analysis is based on
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All of the above
Answer: Option D
Solution (By Examveda Team)
PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM).It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion