PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of the above

Answer: Option D

Solution (By Examveda Team)

PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM).
It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project