Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

A. To have a check on a definitive cost estimate

B. To check quotations from contractors and/or sub-contractors

C. To compute target estimate for the owner while drawing and specifications are in initial stage

D. All of these

Answer: Option D