Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
A. Consumes time, but no resources
B. Consumes resources but no time
C. Consumes neither time nor resources
D. Is a dangling event
Answer: Option C
Solution (By Examveda Team)
Dummy activity on a PERT/CPM chart means, it Consumes neither time nor resourcesRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion

Join The Discussion