Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

A. Consumes time, but no resources

B. Consumes resources but no time

C. Consumes neither time nor resources

D. Is a dangling event

Answer: Option C

Solution (By Examveda Team)

Dummy activity on a PERT/CPM chart means, it Consumes neither time nor resources