Pick up the correct statement from the following
A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project
C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
D. All of the above
Answer: Option D
Solution(By Examveda Team)
- If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed- If the float of an activity is negative, delay in its performance is bound to delay the completion of project
- If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion