Pick up the correct statement from the following
Answer & Solution
Correct Answer:
Option
D
- If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
- If the float of an activity is negative, delay in its performance is bound to delay the completion of project
- If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
- If the float of an activity is negative, delay in its performance is bound to delay the completion of project
- If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project