Prime cost is $50000 and direct manufacturing labour is $10000, then direct material cost will be
Answer & Solution
Correct Answer:
Option
A
Direct material cost = Prime cost - Direct manufacturing labour
= $50000 - $10000 = $40,000
= $50000 - $10000 = $40,000