Slack of various events on the critical path in PERT/CPM chart
A. Increases continuously
B. Decreases continuously
C. Remain constant
D. May increase or decrease depending on various factors
Answer: Option C
Solution (By Examveda Team)
Slack of various events on the critical path in PERT/CPM chart Remain constantRelated Questions on Industrial Engineering and Production Management