Some work to complete in 50 days by 100 men , after 30 days deployment increased by 50%. how many days behind would be the work if additional men not deployed?

Solution(By Examveda Team)

[(100 x 30) + (150 x 20)] men can finish the work in 1 day.
6000 men can finish it in 1 day.
∴ 100 men can finish it in 6000/100 days = 60 days.
This is 10 days behind schedule.