Static budget amount is subtracted from actual result to calculate
A. static budget receipts
B. static budget deviation
C. static budget variance
D. multiple budget variance
Answer: Option C
Solution(By Examveda Team)
Static budget amount is subtracted from actual result to calculate static budget variance. The static budget is used as the basis from which actual results are compared. The resulting variance is called a static budget variance.Related Questions on Management Accounting
A. resourcing
B. value acquiring
C. production
D. value acquaintance
Examining of past performance, exploring alternative and planning future is
A. learning
B. alternating
C. examining
D. deciding
Time that a company takes to create and produce a new product is classified as
A. management factor
B. time factor
C. customer factor
D. chain factor
Purpose of management accounting is to
A. past orientation
B. help banks make decisions
C. help managers make decisions
D. help investors make decision