The aggregates required for one kilometer length of water bound macadam road per meter width and for 10 mm thickness is

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

4 Comments
Aziz Panna
Aziz Panna 6 years ago
1000 m × 0.01 m × 1.20 = 12 m^3 per meter width
Shakil Ahmed
Shakil Ahmed 7 years ago
20 % volume increase due to stone dust
Jitender Negi
Jitender Negi 7 years ago
1000 *1*0•01 =10
20%extra broken stone req.=10+2=12 cumec
Merugu Ravi
Merugu Ravi 8 years ago
L=1000m,b=1m,t=0.01m
Vol.=lbt=1000*1*.01=10m^3