The Boston Big Dig project faced severe delays due to:

A. Magma chamber discovery

B. Sinkhole formation in karst

C. Unexpected soft clay and utility relocations

D. Fault displacement

Answer: Option C

Solution (By Examveda Team)

The Big Dig encountered soft clays, high groundwater levels, and urban infrastructure, necessitating extensive soil stabilization and support.