The feasibility study of an opencast mine revealed the following:
Recoverable value per tonne of ore = Rs. 900
Production cost per tonne of ore = Rs. 550
Stripping cost per tonne of waste = Rs. 45
The break even stripping ratio will be

A. 7.77

B. 32.20

C. 1.78

D. 12.22

Answer: Option A