The following data are provided for a surface mine to be excavated by a shovel:
Production target: 10000 te/shift
Available hours per shift: 6 hrs
Shovel loading cycles per hour: 106
Bank density of the material mined: 2400 kg/m3
Swing factor at 120° swing: 0.91
Bucket fill factor : 0.64
Utilization of available time: 83%
No of working days in a year : 300
No of shifts per day : 3
The size of bucket of the shovel in m3 is
A. 5.55
B. 9.33
C. 11.22
D. 13.55
Answer: Option D
Related Questions on Introduction to Mining Engineering
A. Normal distribution
B. Skewed distribution
C. Lognormal distribution
D. Poisson distribution
A. 3 level heading district
B. 4 level heading district
C. 5 level heading district
D. 6 level heading district
It is very difficult to control shaley roof if coal is not left with the shale why?
A. It is weak in nature
B. It has weathering effect
C. It has great affinity to absorb moisture and get departed from immediate roof
D. It reacts with coaly surface
Join The Discussion