The following method practiced in NECL (Assam) for extraction of steep thick seam.
A. B.G
B. Sublevel caving
C. Bhaska and Tipping
D. Longwal
Answer: Option C
A. B.G
B. Sublevel caving
C. Bhaska and Tipping
D. Longwal
Answer: Option C
The required water for 1 ton of sand in hydraulic sand stowing is . . . . . . . .
A. 800 l
B. 600 l
C. 1100 l
D. 1200 l