The following operations are required for tunnelling in rocky terrain:
1.Removing the foul gases
2.Marking the tunnel profile
3.Setting up and drilling
4.Checking misfire
5.Mucking
The correct sequence is:
A. 1, 2, 3, 4, 5
B. 2, 3, 5, 4, 1
C. 4, 2, 1, 3, 5
D. 2, 3, 1, 4, 5
Answer: Option D