The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time)
A. $$\frac{{{{\text{t}}_{\text{o}}} + {{\text{t}}_{\text{p}}} + {{\text{t}}_{\text{n}}}}}{3}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 2{{\text{t}}_{\text{p}}} + {{\text{t}}_{\text{n}}}}}{4}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{p}}} + {{\text{t}}_{\text{n}}}}}{5}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + {{\text{t}}_{\text{p}}} + 4{{\text{t}}_{\text{n}}}}}{6}$$
Answer: Option D
Solution (By Examveda Team)
The probabilistic time is given by $$\frac{{{{\text{t}}_{\text{o}}} + {{\text{t}}_{\text{p}}} + 4{{\text{t}}_{\text{n}}}}}{6}$$Where to = Optimistic time, tp = Pessimistic time and tn = Most likely time.
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion