The probability distribution of project completion in PERT follows following distribution
A. Normal
B. Binomial
C. Exponential
D. Gaussian
Answer: Option D
Solution (By Examveda Team)
Gaussian distribution is a bell-shaped curve, and it is assumed that during any measurement values will follow a normal distribution with an equal number of measurements above and below the mean value.Join The Discussion