The process of keeping concrete moist for a certain period after its finishing, is known as
A. Finishing of concrete
B. Curing of concrete
C. Placing of concrete
D. Compaction of concrete
Answer: Option B
A. Finishing of concrete
B. Curing of concrete
C. Placing of concrete
D. Compaction of concrete
Answer: Option B
The window which is provided in flat roof of a room, is known
A. Dormer window
B. Lantern window
C. Louvered window
D. Sky window
Weep holes are provided in retaining and breast walls
A. To drain off the water from the filling
B. To ventilate the stone masonry
C. To add architectural beauty
D. To increase compaction of the earth retained
A. Haunch
B. Spandril
C. Voussoirs
D. Skewbacks
Join The Discussion