The sale value of chromite ore from an open pit mine is Rs. 6500 per tonne. Cost of mining, excluding stripping cost, is Rs. 2450 per tonne. If the cost of stripping is Rs. 1150 per m3, the breakeven stripping ratio in m3/tonne is

A. 2.18

B. 3.52

C. 3.65

D. 4.25

Answer: Option B