The sequence of four stages of survey in a highway alignment is
A. reconnaissance, map study, preliminary survey and detailed survey
B. map study, preliminary survey, reconnaissance and detailed survey
C. map study, reconnaissance, preliminary survey and detailed survey
D. preliminary survey, map study, reconnaissance and detailed survey
Answer: Option C
Join The Discussion
Comments ( 1 )
Highway facilities are designed for
A. annual average hourly volume
B. annual average daily traffic
C. thirtieth highest hourly volume
D. peak hourly volume of the year
The provision of traffic signals at intersections
A. reduces right angled and rear end collisions
B. increases right angled and rear end collisions
C. reduces right angled collisions but may increase rear end collisions
D. reduces rear end collisions but may increase right angled collisions
In CBR test the value of CBR is calculated at
A. 2.5 mm penetration only
B. 5.0 mm penetration only
C. 7.5 mm penetration only
D. both 2.5 mm and 5.0 mm penetrations
If aggregate impact value is 20 to 30 percent, then it is classified as
A. exceptionally strong
B. strong
C. satisfactory for road surfacing
D. unsuitable for road surfacing
MRPD yh arrange Hy .Map.reconnassance.preliminary.Detailed survey