The state of every buffer, drawbar of tub, safety catch, coupling chains are examined once atleast in every . . . . . . . . days by competent person.
A. One
B. Seven
C. Fourteen
D. Thirty
Answer: Option C
A. One
B. Seven
C. Fourteen
D. Thirty
Answer: Option C
A. 8 hours
B. 24 hours
C. Weak
D. Month
Who are responsible for implementation of the code of practice in the roadway conveyors
A. Surveyor
B. Under manager
C. Engineer
D. Manager
A. Abonded working
B. Disused working
C. Unused works
D. Discontinued working