The stoping method, where a large part of blasted ore is allowed to accumulate in the stope to serve the purpose of providing working platform for stoping as well as to support the wall-rock, is known as
A. shrinkage stoping
B. cut and fill stoping
C. square-set stoping
D. sublevel stoping
Answer: Option A
Related Questions on Introduction to Mining Engineering
A. Normal distribution
B. Skewed distribution
C. Lognormal distribution
D. Poisson distribution
A. 3 level heading district
B. 4 level heading district
C. 5 level heading district
D. 6 level heading district
It is very difficult to control shaley roof if coal is not left with the shale why?
A. It is weak in nature
B. It has weathering effect
C. It has great affinity to absorb moisture and get departed from immediate roof
D. It reacts with coaly surface