The Tokyo Bay Aqua-Line tunnel used which construction method to combat high water pressure?

A. Earth pressure balance TBM

B. Drill and blast

C. Cut-and-cover

D. Jacked box tunneling

Answer: Option A

Solution (By Examveda Team)

Earth Pressure Balance TBMs were employed to maintain face stability and counteract the high water pressure beneath Tokyo Bay.