The value of ore is Rs. 600 per ton, production cost Rs. 400 per ton and cost of over burden removal is Rs. 50 per m3, the break even stripping ratio in m3/ton is

Answer & Solution
Correct Answer: Option B
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
M Sanapathi
M Sanapathi 10 months ago
(600-400)/50=4/1