The Vasco da Gama bridge construction required which method for dealing with soft clay deposits?

A. Dynamic compaction

B. Deep mixing

C. Surface blasting

D. Geogrid reinforcement

Answer: Option B

Solution (By Examveda Team)

Deep mixing method was used to improve soft clay stability in the Tagus River area during bridge piling operations.