Dhruba Dasgupta
Dhruba Dasgupta
8 years ago

Three diggers dug a ditch of 324 m deep in six days working simultaneously. During one shift, the third digger digs as many meters more than the second as the second digs more than the first. The third digger's work in 10 days is equal to the first digger's work in 14 days. How many meters does the first digger dig per shift?

A. 15

B. 18

C. 21

D. 27

Answer: Option A


This Question Belongs to User Ask Question >> Miscellaneous

Join The Discussion

Comments ( 1 )

  1. Kumar Chandan
    Kumar Chandan :
    8 years ago

    One days work =324/6=54 meters
    Now say first digs x and second digs y meters more then
    x+x+y +x+2y=54 or x+y=18
    And
    10*(x+2y)=14x
    x=5y
    So x=15 meters.

Related User Ask Questions