What factor contributed to excessive ground settlement during the Bangkok Subway construction?
A. Seismic loading
B. Artesian pressure
C. Compressible soft clay
D. Salt dome collapse
Answer: Option C
Solution (By Examveda Team)
Bangkok is built on compressible soft clay, and tunneling caused excessive settlement, requiring pre-construction ground monitoring and compensation grouting.Which geotechnical failure occurred in the 1963 Vajont Dam disaster in Italy?
A. Overtopping of dam
B. Foundation failure
C. Landslide into reservoir
D. Earthquake-induced cracking
What was the main geological issue in the Panama Canal expansion project?
A. Lava flow
B. Marine sediment instability
C. Hard rock tunneling
D. Seismic liquefaction
In the case of the Leaning Tower of Pisa, what caused the leaning?
A. Uneven settlement due to clayey soil
B. Earthquake damage
C. Poor construction material
D. Tectonic movement
Which engineering technique stabilized the Hong Kong slopes after landslide disasters?
A. Tunneling
B. Shotcreting and soil nailing
C. Earth reinforcement
D. Floating raft foundation
Join The Discussion