What factor contributed to excessive ground settlement during the Bangkok Subway construction?

A. Seismic loading

B. Artesian pressure

C. Compressible soft clay

D. Salt dome collapse

Answer: Option C

Solution (By Examveda Team)

Bangkok is built on compressible soft clay, and tunneling caused excessive settlement, requiring pre-construction ground monitoring and compensation grouting.