What geological factor led to construction delay in the Atal Tunnel project?

A. Seismicity

B. Fault zone with water ingress

C. High altitude logistics

D. Glacial movement

Answer: Option B

Solution (By Examveda Team)

The fault zone with water ingress in the Seri Nallah section led to excessive inflow of water and unstable tunneling conditions, causing delays and the need for additional support systems.