Examveda

What monitoring method was used in the Sikkim Hydro Project to track tunnel deformation?

A. Resistivity imaging

B. Seismic tomography

C. Convergence meters

D. Satellite imaging

Answer: Option C

Solution (By Examveda Team)

Convergence meters measure the inward movement of tunnel walls. They were used in the Sikkim Hydro Project to assess tunnel stability under high stress and fractured rock.