What technique was used in the Palm Jumeirah project to stabilize reclaimed land?

A. Deep foundation piles

B. Vibro-compaction

C. Soil freezing

D. Rock anchors

Answer: Option B

Solution (By Examveda Team)

Vibro-compaction was used to densify loose sand deposits, improving bearing capacity and reducing settlement on this artificial island.