What was the key lesson from the Nicoll Highway collapse in Singapore (2004)?
A. Errors in tunneling method
B. Traffic overloading
C. Soil-structure interaction underestimated
D. Poor rock anchoring
Answer: Option C
Solution (By Examveda Team)
The collapse was due to underestimated soil-structure interaction during diaphragm wall construction in soft clay conditions.Which geotechnical failure occurred in the 1963 Vajont Dam disaster in Italy?
A. Overtopping of dam
B. Foundation failure
C. Landslide into reservoir
D. Earthquake-induced cracking
What was the main geological issue in the Panama Canal expansion project?
A. Lava flow
B. Marine sediment instability
C. Hard rock tunneling
D. Seismic liquefaction
In the case of the Leaning Tower of Pisa, what caused the leaning?
A. Uneven settlement due to clayey soil
B. Earthquake damage
C. Poor construction material
D. Tectonic movement
Which engineering technique stabilized the Hong Kong slopes after landslide disasters?
A. Tunneling
B. Shotcreting and soil nailing
C. Earth reinforcement
D. Floating raft foundation