What was the major geological issue in the Chunnel (Channel Tunnel) project?
A. Water ingress in chalk marl
B. Rockburst
C. Thermal cracking
D. Fault slip zones
Answer: Option A
Solution (By Examveda Team)
The Channel Tunnel passed through chalk marl, which presented groundwater control issues. Pressurized TBMs and sealing techniques were used to handle water ingress.Which geotechnical failure occurred in the 1963 Vajont Dam disaster in Italy?
A. Overtopping of dam
B. Foundation failure
C. Landslide into reservoir
D. Earthquake-induced cracking
What was the main geological issue in the Panama Canal expansion project?
A. Lava flow
B. Marine sediment instability
C. Hard rock tunneling
D. Seismic liquefaction
In the case of the Leaning Tower of Pisa, what caused the leaning?
A. Uneven settlement due to clayey soil
B. Earthquake damage
C. Poor construction material
D. Tectonic movement
Which engineering technique stabilized the Hong Kong slopes after landslide disasters?
A. Tunneling
B. Shotcreting and soil nailing
C. Earth reinforcement
D. Floating raft foundation