Which of the following is an example of proactive geotechnical monitoring in large-scale tunneling?

A. GPR survey before excavation

B. Preloading of soil

C. Use of surface tiltmeters and extensometers

D. Use of blasting in hard rock

Answer: Option C

Solution (By Examveda Team)

Surface tiltmeters and extensometers are widely used in real-time monitoring of ground movement during tunneling to prevent failures.