Which of the following is approximately correct for average resource utilization?
A. $$\frac{{{\text{sum of all task times}}}}{{{\text{cycle time}}}}$$
B. $$\frac{{{\text{sum of all task times}}}}{{{\text{number of work stations }} \times {\text{ cycle time}}}}$$
C. $$\frac{{{\text{available time}}}}{{{\text{actual production}}}}$$
D. none of the above
Answer: Option B